Monte Carlo: more paths vs smaller time steps
A beginner's guide to the two knobs of a Monte Carlo pricer. More paths reduce random noise. Smaller time steps reduce bias. Worked examples with real simulated numbers.
A Monte Carlo pricer has two main settings. One is how many paths it simulates. The other is how many time steps each path takes. They fix different errors. This page shows both with real numbers from a small simulation.
The example used on this page
Section titled “The example used on this page”Everything below uses the same stock and the same Black–Scholes model.
| Symbol | Meaning | Value |
|---|---|---|
| Stock price today | 100 | |
| Strike of the option | 100 | |
| Interest rate (continuous) | 2% | |
| Volatility (yearly) | 20% | |
| Time to expiry, in years | 1 | |
| Barrier level (used later) | 120 |
All values are shown per contract of 100 shares, in USD. A per-share price of 8.916 shows as 891.6. This keeps the charts readable.
Two products appear:
- A European call. It pays at expiry. Here is the stock price at time . The exact price from the Black–Scholes formula is 891.6 per contract.
- An up-and-out call. It is the same call, but it dies (pays nothing) if the stock ever touches before expiry. The exact price, from the standard closed-form formula for a continuously watched barrier, is 114.1 per contract.
What a Monte Carlo pricer does
Section titled “What a Monte Carlo pricer does”A Monte Carlo pricer guesses the price by playing out many random futures.
- Simulate one possible future of the stock. This is one path.
- Work out what the option pays on that path.
- Repeat many times.
- Average the payoffs and discount them to today.
flowchart LR A["Draw random numbers"] --> B["Build one stock path"] B --> C["Apply the payoff rule"] C --> D["Repeat N times"] D --> E["Average and discount"] E --> F["Price estimate"]
In symbols, with paths and the final price on path :
The hat on means “estimate”. It is not the true price . It is close to it, and the gap is what this page is about.
Paths and time steps
Section titled “Paths and time steps”A path is built one small jump at a time. Split the year into equal time steps. Each step has length . One step moves the stock like this:
Here is a fresh standard normal random number for each step.
Four paths from the formula above with weekly steps. Each dot is one step. The call pays per share if a path ends above 100, and nothing otherwise.
So there are two numbers to choose:
| Knob | Symbol | Example |
|---|---|---|
| Number of paths | 10,000 or 1,000,000 | |
| Steps per path | (step size ) | 12 monthly, 52 weekly, 252 daily |
The total work is roughly random numbers.
Knob 1: more paths shrink the noise
Section titled “Knob 1: more paths shrink the noise”Every run of the pricer uses different random numbers. So every run gives a slightly different answer. This scatter is Monte Carlo noise.
You can measure the noise from the run itself. Let be the standard deviation of the discounted payoffs across paths. The standard error of the average is:
A 95% confidence band is the estimate plus or minus . It is the range where the true price usually sits, if the pricer has no other error.
Here is one run of the European call. The run keeps adding paths, and we read the estimate at six points along the way.
One seeded run of the European call. The band narrows as grows and always contains the exact price 891.6. The estimate wanders inside the band; that wandering is noise.
The band shrinks from ±41.8 at 4,000 paths to ±8.5 at 100,000 paths. The centre of the band stays on the exact price. Nothing is systematically wrong here, so more paths are the right fix.
The square-root rule
Section titled “The square-root rule”The noise falls like , not like . That is slow.
- 4 times more paths cut the noise in half.
- 100 times more paths cut the noise by a factor of 10.
To check this, we ran the call pricer 200 times at each , each with a different seed. Then we measured how much the 200 answers spread out. The chart compares that spread with the formula.
Spread of 200 independent estimates (one standard deviation) vs the standard error formula, with per contract. The two lines match. From 4,000 to 16,000 paths the noise halves; from 25,000 to 100,000 it halves again.
Worked example. Say you want the call to within ±1 per contract (95%). Solve . That gives million paths. Getting ±2 needs only a quarter of that, about 1.8 million. Each extra digit of accuracy costs 100 times the paths.
Knob 2: smaller steps shrink the bias
Section titled “Knob 2: smaller steps shrink the bias”For the European call, only matters. In this model one big step from today to expiry gives the exact distribution of . So is enough, and time steps never cause an error.
Many products are different. They look at the whole path:
- A barrier option dies (or comes alive) if the price touches a level at any time.
- An Asian option pays on the average price over many dates.
- A model where volatility changes with the stock price (a local volatility model) only has an approximate step formula. Big steps drift away from the model.
For these, a coarse grid prices a slightly different product. That error is bias: it pushes every run the same way. It does not average out.
flowchart TB
Q{"Does the payoff or the model need the path between dates?"}
Q -->|"No, only the final price"| One["Few steps are fine; spend on paths"]
Q -->|"Yes, e.g. barrier or local vol"| Many["Step size matters; check bias first"]
More paths cannot fix a coarse grid
Section titled “More paths cannot fix a coarse grid”Take the up-and-out call. Its barrier is watched all the time, so the exact price is 114.1. A simple pricer checks the barrier only at its time steps. Between steps, the stock can touch 120 and come back unseen. See Barriers between time steps for the full story.
Here are two engines, each run with more and more paths.
Each line is one seeded run read at six path counts. Adding paths makes both lines flatter, but neither line moves toward 114.1. Only a finer grid (or a correction) moves the level.
Now compare three runs with about the same effort:
| Engine | Steps | Paths | Estimate ± 95% band | Gap to 114.1 |
|---|---|---|---|---|
| Monthly, huge run | 12 | 1,000,000 | 177.1 ± 0.8 | +63.0 |
| Daily, small run | 252 | 20,000 | 127.1 ± 4.7 | +13.0 |
| Monthly + bridge fix | 12 | 20,000 | 113.1 ± 3.9 | −1.0 |
The first row looks the most “precise”. Its band is under one dollar wide. It is also the most wrong. A tight band only says the runs agree with each other. It does not say they agree with the true price.
The third row uses a Brownian-bridge correction, explained on the barrier page. It removes the bias without extra steps.
Precision is not accuracy
Section titled “Precision is not accuracy”Picture a dartboard. The bullseye is the true price. Each run is a dart.
- Precision: the darts land close together (small noise).
- Accuracy: the darts land around the bullseye (small bias).
flowchart LR A["Many paths, coarse steps"] --> A2["Tight cluster, off target"] B["Few paths, fine steps"] --> B2["Loose cluster, on target"] C["Enough of both"] --> C2["Tight cluster, on target"]
Paths buy precision. Steps (or a smarter barrier check) buy accuracy.
Splitting a fixed compute budget
Section titled “Splitting a fixed compute budget”In practice the pricer gets a fixed amount of time. Say it can afford path-steps for the up-and-out call. More steps means fewer paths. What is the best split?
Same budget at every point: . Bias was measured with a separate 200,000-path run per grid. Noise uses the standard error at the budget’s path count. Bias falls as steps grow; noise rises as paths shrink.
| Steps | Paths | Bias | Noise (95%) | Bigger error |
|---|---|---|---|---|
| 4 | 315,000 | 104.1 | 1.6 | bias |
| 12 | 105,000 | 64.0 | 2.5 | bias |
| 52 | 24,231 | 32.5 | 4.6 | bias |
| 252 | 5,000 | 14.7 | 9.4 | bias |
Bias is the bigger error in every row. So for this product, extra steps are worth more than extra paths. The simple rule:
- Make the grid fine enough (or add a correction) until the price stops moving when you halve .
- Then add paths until the band is as tight as you need.
If halving moves the price by more than the band width, buying more paths is the wrong spend.
How this is used in practice
Section titled “How this is used in practice”- Overnight risk runs. A trading desk reprices every trade many times each night: once for the price, and again for each bumped input (spot, vol, rates) to get the Greeks. The total time is fixed, so each product type gets a chosen path count and step grid. Simple payoffs get few steps and many paths. Path-dependent payoffs get finer grids.
- The grid always includes contract dates. Fixing dates, barrier observation dates and payment dates are always time steps. Extra steps are added between them only when the payoff or the model needs them.
- Same seed for bumps. When computing a Greek, the base and bumped prices use the same random numbers. The noise then mostly cancels in the difference.
- Report the band. A Monte Carlo price is usually reported with its standard error, so users can see how noisy it is.
- Cheaper noise reduction. Tricks such as antithetic paths (use and ) or a control variate (price a similar product with a known formula, such as the European call, and correct by its known error) cut noise without extra paths. They do not remove bias.
- Convergence checks. Before trusting a new product setup, quants rerun it with half the step size and with four times the paths. If the price moves more than the band, the grid is too coarse.
Quick checklist
Section titled “Quick checklist”- Noise: shrinks like . Visible as a confidence band.
- Bias: comes from the grid or the model steps. Invisible in the band.
- A tight band around a coarse grid is a tight band around the wrong number.
- Fix bias first (steps or corrections), then buy paths.
Where this shows up
Section titled “Where this shows up”Path-dependent exotics all face this trade-off: barrier options, Asian options, and autocallables.
See also
Section titled “See also”- Barriers between time steps: why a grid misses barrier touches, and two cheap fixes.
- Concepts